23 Bay night installation in Birmingham

14th December 2018

We have supplied several buildings to UTC over the years. This time we provided a special night time installation, over 6 nights, from 11pm to 5am.

Our client is based at the end of Birmingham Airport runway, so the new building had to go in during runway maintenance time. The accommodation will be used by senior management, and as a customer reception.

It’s unusual to be in constant contact with air traffic control during modular building installations. It certainly added an extra interesting element to our Health and Safety procedures!

The building was supplied as a shell only. We’re due back in February to complete the final works, including the skirt and floor coverings looking for san diego airport to escondido service. With bespoke high ceilings and internal configuration, it will be fascinating to see the completed product.

You may also like

Several multispan temporary warehouses with a steel portal framed building construction.
13th August 2026 BlogsPortable Buildings

Portal Frame Buildings with Office Space

11th August 2026 BlogsPortable Buildings

Safety Standards for Portable Buildings: Electrical, Gas, and Water Compliance Explained

How can we help you with your next project?

Image of PBS team