< Back to Blog

We skate Portable Buildings into smaller factory spaces

We recently provided Illuminate with a new manufactured 24′ x 10′ open plan portable building which was delivered using a...

Contact Us

We recently provided Illuminate with a new manufactured 24′ x 10′ open plan portable building which was delivered using a hi-ab craned vehicle.

Unfortunately the factory roof was not high enough to unload the building inside the factory, so we sent one of our teams down who unloaded the Jack Leg Cabin outside the factory and then skated it inside before leveling the building. Another very happy customer.

< Back to Blog

More Classrooms for Fairfield Primary Academy

We were pleased to once again be approached by Fairfield Primary Academy in Nottingham to supply them with a further...

Contact Us

We were pleased to once again be approached by Fairfield Primary Academy in Nottingham to supply them with a further two classroom buildings. We previously supplied the school with a 3 section modular classroom building and they were so delighted with our product and service that they contacted us again to supply new matching buildings.

Malcolm Lucas the Head of Estates and Facilities ordered a 12m x 6m 2 section open plan classroom with a toilet and disabled toilet facility / entrance area and a 3 section open plan classroom with the same toilet facilities.

As part of our contract we were asked to also undertake the safe delivery and installation of the new modular buildings and the ground work requirements.

As you can see on the photographs, the entrance to the school was particularly tight, but having arranged a free site survey by the transport company, we were confident of successfully delivering the modules to their final location.