Purchasing additional classroom space often takes time and in the case of Campion school in Bugbrooke, Northamptonshire, their Facilities Manager...
Posted on 11th September 2014 Contact Us
Purchasing additional classroom space often takes time and in the case of Campion school in Bugbrooke, Northamptonshire, their Facilities Manager originally contacted us in May 2013 to obtain some costs for a feasibility study.
They required an additional classroom, for use as a teaching space, for 6 to 10 students with a separate private room area for introducing students back into education.
After receiving our costs, we were asked to conduct a site survey in July 2013 and then they applied for planning and started a consultation period with a view to receiving a building in the summer of 2014.
We delivered and installed their new Clearview Building last week, well in time for the new September term.